Ambiens Projects

New homes, Foxrock, Dublin 18

In progress

Four new detached family homes in the garden of a protected period house, and the restoration of that house.

Guest bedroomConcept image until the client approves real photos
Guest bedroom
Scheme
4 detached homes and 1 protected house
Homes
Two storeys, four bedrooms, about 193 m² each
Energy
A2 provisional BER, about 35–37 kWh/m² a year
Completion
To be confirmed
The site

A site of about 3,100 m²: a large garden behind a protected period house. The new homes had to respect the protected structure, keep the mature trees and use the existing entrance from the main road. The garden's old outbuildings and hard court were cleared before building began.

What the project covered
  • Site checks
  • Architectural design
  • Planning permission
  • Planning conditions
  • Conservation works
  • Tender and contract
  • Utility connections
  • Building control
  • Structural warranty
  • New-build construction
The period house
  • Works overseen by a conservation-accredited architect
  • Lime render repairs and re-pointed brickwork
  • Breathable internal insulation
  • Re-roofed with salvaged slates
  • Modern conservatory, carport and pool house removed
  • Radon barrier and a new ground floor
Specification
  • Concrete construction with precast concrete floor and roof slabs
  • External wall insulation, natural stone and timber-effect cladding
  • Walls and floors at U-value 0.18, flat roofs at 0.20, windows averaging 1.21
  • Air-to-water heat pump, 200-litre hot water cylinder, underfloor heating
  • Whole-house mechanical extract ventilation
  • Copper-clad projecting bay windows and precast concrete stairs
  • Permeable paving that lets rainwater soak away on site
  • Landscaped gardens, 8 parking spaces, original boundary walls restored
How it ran
  1. 2021
    Site checksPlanning history, protected status, access, trees, drainage and utility capacity
  2. 2021–2022
    DesignTwo house types, two homes of each, with flat roofs and copper-clad bays
  3. 2022–2024
    Planning permissionGranted by the council; confirmed on appeal
  4. 2023
    The period houseConservation works to the protected house
  5. 2024
    Planning conditionsConstruction, waste, noise and dust plans, tree protection, landscaping and utility agreements, all before work starts
  6. April 2024
    Building regulationsCommencement notice lodged; statutory inspection and certification throughout
  7. July–October 2024
    Tender and contractMain contractor appointed on a recognised building contract
  8. 2025
    Structural warrantyAll four homes registered for a 10-year structural warranty, with stage inspections
  9. 2024–2025
    UtilitiesWater and wastewater with Uisce Éireann, electricity with ESB Networks
  10. Build progress: to be confirmed
    BuildFoundations, concrete structure, roofs, insulation and cladding, first-fix services
  11. Fit-out progress: to be confirmed
    Fit-out and joineryPlastering, tiling, second-fix services, kitchens, joinery and stairs, painting and floors
  12. To be confirmed
    HandoverAir-tightness test, final BER, compliance certificates, snagging
What this project shows
  • A garden site behind a period house is never just four houses: protected-structure rules, trees, overlooking and shared access all shape the design.
  • On sensitive sites, allow time for an appeal in both the programme and the finance.
  • Planning conditions are a work stage of their own. Each plan needs an owner and a deadline before the first digger arrives.
  • Start water and electricity applications early; they run on the utilities' own timelines.
  • The energy rating is set at design stage and decided on site by air-tightness.
  • Warranty and certification records are what make a new home saleable.